How to tell which action was taken from a multi action task/fixlet

Is there a way to tell from a multi-action task/fixlet, which action was taken when the task/fixlet is running? eg. Should there be something in the Actions Summary tab to indicate this?

Not clear on ask here :frowning: if you can elaborate

As per above example, ILMT has a fixlet called
Run Capacity Scan and Upload Results (9.2.44.0)

and it has 2 possible actions to choose from. When the action is submitted an running, is there a way to tell which of the above 2 action options were selected?

The easiest and simplest way is to check the action script which one is running. Compare from action1 and action2 of the fixlet/task. Let us know if this helps

The Baseline itself will list which Action is selected for each component, that's the easiest place to look.
Action1 vs Action2 does not toggle from one computer to another, only one action is assigned in the Baseline Component.

I don’t run any baselines with ILMT. That’s fine, I was just wondering if this info was shown somewhere in the active action, but it looks like its not.

Thanks for all your feedback.

Regards … Leslie