Hello, I was wondering if any one has experience on how the End time for a baseline is calculated an presented in the Big fix console.
this is my scenario
Baseline A with 20 Patches
Start time 19
the log reads
At 21:22:29 +0000 -
ActionLogMessage: (action:3379) ending group action (completed)
At 22:35:16 +0000 - Enterprise Security (http://sync.bigfix.com/cgi-bin/bfgather/bessecurity)
Fixed - 4042076: Security and Quality Rollup for .NET Framework 3.5.1 for Windows 7 SP1 and Windows Server 2008 R2 SP1 - Windows Server 2008 R2 SP1 - .NET Framework 3.5.1 - KB4040980 (x64) (fixlet:404207621)
After that nothing happens on the server, hence I am assuming that there is nothing else to do.
The server in the GUI reports the end time as: 03/02/2018 21:22:29
Baseline B with 23 Patches (same 20 as above plus 3)
Start time 19
the log reads:
At 21:55:09 +0000 -
ActionLogMessage: (action:4031) ending group action (completed)
At 23:25:40 +0000 - Enterprise Security (http://sync.bigfix.com/cgi-bin/bfgather/bessecurity)
Fixed - MS17-OCT: Security Only Quality Update - Security Only - Windows Server 2008 R2 SP1 - KB4041678 (x64) (fixlet:404167803)
Fixed - 4042076: Security and Quality Rollup for .NET Framework 3.5.1 for Windows 7 SP1 and Windows Server 2008 R2 SP1 - Windows Server 2008 R2 SP1 - .NET Framework 3.5.1 - KB4040980 (x64) (fixlet:404207621)
Report posted successfully
After that nothing happens on the server, hence I am assuming that there is nothing else to do.
The server in the GUI reports the end time as: 05/02/2018 05:48:12
Question here is…why in scenario B the end time is reported as 7 hours (aprox) after the ending action group date/time?
Any one knows why the behavior or better yet, what part of the log will trigger the end time on Big FIX gui?
Thanks.