Tie an action item to run after a baseline becomes complete

(imported topic written by mdewitt72)

Is there a way to tie an action item to run after a baseline status becomes complete for a computer.

(imported comment written by jessewk)

  1. Add it as the last item in the baseline

  2. Place a custom action script in the ‘Post-Execution Action Script’ tab when taking the baseline action.