Someone suggested using a baseline could cause the execution of a task and the analysis that reports up the results together one after the other and the baseline could then be scheduled as a single recurring event. Does this sound possible?

I have not found anything in my forum searches so far.

(imported comment written by SystemAdmin)

Hey Robmuh,

Analyses dont have actions the same way a task does, so you cannot include it in a baseline in this way. Once activated, an analysis will evaluate itself periodically, and report up any changes that may occur.

This means that you can activate your analysis once, and any time you run your task the analysis will automatically report the changes (assuming the task changes something that the analysis is reporting on), so you typically dont have to worry about coupling the tasks to the analysis in a baseline.